Corpus Christi Liquefaction August 2017 Monthly Progress Report   

info • Sep 21, 2017

The total project has progressed to 71.7% complete against the plan of 72.1%.

On September 21, 2017 Cheniere Energy submitted a monthly progress report to the U.S. Federal Energy Regulatory Commission for the Corpus Christi Liquefaction project. The report covers activities of the project that occurred during the month of August 2017.

The report noted engineering has progressed to 100.0%. Procurement has progressed to 89.2%. Subcontract and direct hire construction work are 47.8% and 48.0% complete, respectively. The total project has progressed to 71.7% complete against the plan of 72.1%.

Construction focused on progressing permanent plant concrete, structural steel, aboveground pipe, electrical and equipment installation. Major highlights for August included setting the Train 1 filter houses, handover of the west jetty to the OSBL LNG team, installation of the first remediated galvanized spools and the continuation of high voltage work in preparation for GIS and main substation energization.

Images below from the FERC Corpus Christi Liquefaction monthly construction report for August 2017.

Corpus Christi LNG
Corpus Christi LNG
Corpus Christi LNG
Corpus Christi LNG
Corpus Christi LNG

Receive the most important LNG headlines in your email inbox each business day. Just sign up for our FREE LNG Headline Daily Newsletter. Sign Up Here.

Share by: