Blog Post

Corpus Christi Liquefaction September 2017 Monthly Progress Report 

info • Oct 24, 2017

The overall project has progressed to 72.4% against the plan of 74.1%. Activities planned for the month of October 2017 are on track.

On October 23rd, 2017 Cheniere Energy submitted a monthly progress report to the U.S. Federal Energy Regulatory Commission for the Corpus Christi Liquefaction project. The report covers activities of the project that occurred during the month of September 2017.

The report noted engineering has progressed to 100.0%. Procurement has progressed to 89.4%. Subcontract and direct hire construction work are 49.4% and 49.2% complete, respectively. The total Project has progressed to 72.4% complete against the plan of 74.1%.

The jobsite was closed from August 24 to September 10, 2017. Upon return, Construction started recovery effort from Hurricane Harvey impact and continued progressing permanent plant concrete, structural steel, aboveground pipe, electrical and equipment installation. Major highlights for September included preassembly of the flare and commencement of stacking, compressor lube oil pipe tests and the 3 systems which were turned over to startup.

Images below from the FERC Corpus Christi Liquefaction monthly construction report for September 2017.

Corpus Christi Liquefaction LNG Status Report
Corpus Christi Liquefaction LNG Status Report
Corpus Christi Liquefaction LNG Status Report
Corpus Christi Liquefaction LNG Status Report
Corpus Christi Liquefaction LNG Status Report
Corpus Christi Liquefaction LNG Status Report

Receive the most important LNG headlines in your email inbox each business day. Just sign up for our FREE LNG Headline Daily Newsletter. Sign Up Here.

Share by: