Blog Post

Corpus Christi Liquefaction November 2017 Monthly Progress Report

info • Dec 21, 2017

The overall project has progressed to 77.4%. Activities planned for the month of December 2017 are on track.

On December 20th, 2017 Cheniere Energy submitted a monthly progress report to the U.S. Federal Energy Regulatory Commission for the Corpus Christi Liquefaction project. The report covers activities of the project that occurred during the month of November 2017.

The report noted engineering has progressed to 100.0%. Procurement has progressed to 93.9%. Subcontract and direct hire construction work are 56.1% and 55.8% complete, respectively. The total Project has progressed to 77.4% complete against the plan of 80.8%.

Construction continued progressing permanent plant concrete, structural steel, aboveground pipe, electrical, instruments, and equipment installation. Major highlights for November include: setting Train 1 gas turbine stacks, waste heat recovery units and filter houses; energization of BOG/utility substation; starting above ground pipe insulation; erection of process flare derrick structure; and commencing Train 2 cryo rack air coolers installation. Construction has turned 41 systems over to startup through the end of November.

Images below from the FERC Corpus Christi Liquefaction monthly construction report for November 2017.

Corpus Christi Liquefaction November 2017 Monthly Progress Report
Corpus Christi Liquefaction November 2017 Monthly Progress Report
Corpus Christi Liquefaction November 2017 Monthly Progress Report
Corpus Christi Liquefaction November 2017 Monthly Progress Report
Corpus Christi Liquefaction November 2017 Monthly Progress Report
Corpus Christi Liquefaction November 2017 Monthly Progress Report
Corpus Christi Liquefaction November 2017 Monthly Progress Report

Receive the most important LNG headlines in your email inbox each business day. Just sign up for our FREE LNG Headline Daily Newsletter. Sign Up Here.

Share by: