Corpus Christi Liquefaction Monthly Construction Report for April 2017 

info • May 24, 2017

Overall project has progressed to 61.7%.

Train 1- Installation of Cold Box

On May 23rd, 2017 Corpus Christi Liquefaction, LLC submitted a monthly construction progress report to the Federal Energy Regulatory Commission for the Corpus Christi Liquefaction Project in Corpus Christi, Texas. The report covered activities for Corpus Christi Liquefaction Project during the month of April 2017.

The report noted the overall project has progressed to 61.7%. Activities planned for the month of May 2017 are on track.

Engineering has progressed to 100.0%. Procurement has progressed to 81.4%. Subcontract and direct hire construction work are 31.1% and 33.7% complete, respectively. The total Project has progressed to 61.7% complete against the plan of 62.2%.

Construction focused on progressing permanent plant concrete and steel, underground and aboveground pipe, electrical and equipment installation. Major highlights for April included setting Train 1 Cold Boxes, setting Train 2 Refrigeration Compressors, concrete placement for LNG Tank C roof, placement of all IAC modules and installation of high voltage OPGW cable on all poles.