Blog Post

Corpus Christi Liquefaction June 2018 Monthly ProgressReport

info • Jul 25, 2018

Train 1 is projected to achieve substantial completion in the 1st half of 2019 and Train 2 in the 2nd half of 2019. Activities planned for the month of July 2018 are on track.

On July 23rd, 2018 Cheniere Energy submitted a monthly progress report to the U.S. Federal Energy Regulatory Commission for the Corpus Christi Liquefaction project (CCL). The report covered activities for the CCL Stage 1 (Trains 1 and 2, Tanks A and C, OSBL, West Jetty and East Jetty Civil Works) and CCL Stage 2 (Train 3, Tank B and East Jetty Topsides) projects that occurred during the month of June 2018.

The report noted Stage 1 Engineering and Procurement are now 100.0% complete. Subcontract and direct hire construction work are 75.9% and 77.8% complete, respectively. Overall project completion for Stage 1 is 89.9%. Train 1 is projected to achieve substantial completion in the 1st half of 2019 and Train 2 in the 2nd half of 2019. Stage 2 Engineering is 61.4% complete. Procurement is 47.3% complete. Subcontract and direct hire construction work are 2.6% and 2.9% complete, respectively. Overall project completion for Stage 2 is 28.7%.

Stage 1 continued progressing work in pipe completion, testing, restoration, and insulation of critical path systems. The activities on the refrigeration compressor deck continue to progress as the team prepares for first fire and mechanical runs. In June, the OSBL team focused on the flare systems. Major highlights for June included: completing all initial flushes of the mineral and synthetic oil systems in Train 1 refrigeration compressors, completion of all Train 1 turbine cold cranks, water treatment plant commissioning, and completion of all major Train 1 cold box piping tie-ins. LNG Tank A is preparing for the loading of perlite. Construction has turned 169 systems over to Startup through the end of June.

Stage 2 continued site preparation, mudmat placement, and placement of concrete foundations and columns/pedestals. The team continued design development for Train 3 and OSBL East Jetty. The major placements during June included: ethylene refrigeration compressor foundation and a portion of the compressor deck columns. The underground high-density polyethylene (“HDPE”) pipe welding and installation continued. Installation of metallic amine pipe commenced this period.

Images below from the FERC Corpus Christi Liquefaction monthly construction report for June 2018.

Corpus Christi Liquefaction project (CCL)
Corpus Christi Liquefaction project (CCL)
Corpus Christi Liquefaction project (CCL)
Corpus Christi Liquefaction project (CCL)
Corpus Christi Liquefaction project (CCL)
Corpus Christi Liquefaction project (CCL)
Corpus Christi Liquefaction project (CCL)

Receive the most important LNG headlines in your email inbox each business day. Just sign up for our FREE LNG Headline Daily Newsletter. Sign Up Here.

Share by: