Corpus Christi Liquefaction February 2018 Monthly Progress Report

info • Mar 28, 2018

Train 1 is projected to achieve substantial completion in the 1st half of 2019 and Train 2 in the 2nd half of 2019. Activities planned for the month of March 2018 are on track.

On March 22nd, 2018 Cheniere Energy submitted a monthly progress report to the U.S. Federal Energy Regulatory Commission for the Corpus Christi Liquefaction project (CCL). The report covered activities for the CCL Stage 1 (Trains 1 and 2, Tanks A and C, OSBL, West Jetty and East Jetty Civil Works) and CCL Stage 2 (Train 3, Tank B and East Jetty Topsides) projects that occurred during the month of February 2018.

The report noted Stage 1 Engineering and Procurement are now 100.0% complete. Subcontract and direct hire construction work are 66.3% and 64.3% complete, respectively. Overall project completion for Stage 1 is 84.0%. Train 1 is projected to achieve substantial completion in the 1st half of 2019 and Train 2 in the 2nd half of 2019.

Stage 2 engineering continued. Procurement placed additional long lead time purchase orders. Site civil works continued.

Stage 1 continued progressing work in pipe completion, testing, and critical path systems. In February, the OSBL work focused on the water treatment plant and compressed air generation unit to be ready to turn over to the commissioning and startup team in the next two months. Major highlights for February included: flushing synthetic oil systems in Train 1 refrigeration compressors, preparation for installation of dry gas seals, completion of testing feed gas lines, and energization of the control building substation in the OSBL. Construction has turned 76 systems over to the commissioning and startup team through the end of February.

Stage 2 continued site preparation, drainage activities, mudmat placement, and sheet pile driving. The team commenced welding and installation of underground high-density polyethylene (“HDPE) pipe, installation of rebar, and installation of formwork.

Images below from the FERC Corpus Christi Liquefaction monthly construction report for February 2017.

Corpus Christi Liquefaction February 2018 Monthly Progress Report
Corpus Christi Liquefaction February 2018 Monthly Progress Report
Corpus Christi Liquefaction February 2018 Monthly Progress Report
Corpus Christi Liquefaction February 2018 Monthly Progress Report
Corpus Christi Liquefaction February 2018 Monthly Progress Report
Corpus Christi Liquefaction February 2018 Monthly Progress Report
Corpus Christi Liquefaction February 2018 Monthly Progress Report
Corpus Christi Liquefaction February 2018 Monthly Progress Report

Receive the most important LNG headlines in your email inbox each business day. Just sign up for our FREE LNG Headline Daily Newsletter. Sign Up Here.

Share by: