Train 1 is projecting substantial completion for March 2019 and Train 2 is projecting September 2019 for substantial completion. Activities planned for the month of January 2018 are on track.

On January 23rd, 2018 Cheniere Energy submitted a monthly progress report to the U.S. Federal Energy Regulatory Commission for the Corpus Christi Liquefaction project (CCL). The report covers activities for the CCL Stage 1 (Trains 1 and 2, Tanks A and C, OSBL and East Jetty Civil Marine) and CCL Stage 2 (Train 3 and Tank B and East Jetty Topsides) projects that occurred during the month of December 2017.

The report noted Stage 1 Engineering and Procurement are now 100.0%. Subcontract and direct hire construction work are 66.2% and 59.2% complete, respectively. Overall project completion for Stage 1 is 77.4% complete against the plan of 81.8%. Train 1 is projecting substantial completion for March 2019 and Train 2 is projecting September 2019 for substantial completion.

Stage 2 Engineering has progressed to 25% complete. Procurement has placed 25 critical purchase orders (POs) through the end of December 2017. Subcontract hires are in place to support Train 3 activities.

Stage 1 Construction continued progressing permanent plant concrete, structural steel, aboveground pipe, electrical, instruments, insulation, equipment installation, East Jetty activities and LNG Tank A and C activities. Mineral lube oil flushes for compressors continued. Major highlights for December included: setting Train 2 filter houses and air coolers, the commencement of riser erection on Flare Derrick structure, the energization of the O&M/Control Room building and Train 1 LNG compressor substation. In addition, the air cooler deliveries were completed for the Inlet Air Chiller area. Construction has turned 55 systems over to Startup through the end of December, 3 systems ahead of the scheduled turnover skyline.

Stage 2 Construction mobilized equipment, cleared the Train 3 area, and commenced site work and site drainage activities.

Images below from the FERC Corpus Christi Liquefaction monthly construction report for December 2017.

Corpus Christi Liquefaction
Corpus Christi Liquefaction
Corpus Christi Liquefaction
Corpus Christi Liquefaction
Corpus LNG
LNG Texas

Receive the most important LNG headlines in your email inbox each business day. Just sign up for our FREE LNG Headline Daily Newsletter. Sign Up Here.

Share by: