Sabine Pass Liquefaction & Expansion Monthly Progress Report for May, 2017

  • By Admin
  • 26 Jun, 2017

Train 4 is projecting November 2017 for substantial completion. Train 5 is projecting August 2019 for substantial completion

On June 23rd, 2017 Cheniere Energy submitted a monthly construction progress report to the Federal Energy Regulatory Commission for the Sabine Pass Liquefaction Project in Cameron Parish, Louisiana.

The report covered activities for the Sabine Pass Liquefaction Stage 2 (Trains 3 and 4) and Sabine Pass Liquefaction Stage 3 (Trains 5 and 6) projects that occurred during the month of May 2017.

The report noted Stage 2 Engineering and Procurement are 100% complete. Subcontract and direct hire construction work are 91.0% and 97.1% complete, respectively. Overall project completion for Stage 2 is 98.1% complete against the plan of 100%.

Stage 3 Engineering is now 99.7% complete. Procurement is now 96.2% complete. Subcontract and direct hire work are 47.4% and 26.3% complete, respectively. Stage 3 overall project completion is 67.2% against the plan of 65.7%.

Train 4 is projecting November 2017 for substantial completion. Train 5 is projecting August 2019 for substantial completion.

Sabine LNG Status Report May 2017