Blog Post

Sabine Pass Liquefaction & Expansion Monthly Progress Report for May, 2017

info • Jun 26, 2017

Train 4 is projecting November 2017 for substantial completion. Train 5 is projecting August 2019 for substantial completion

On June 23rd, 2017 Cheniere Energy submitted a monthly construction progress report to the Federal Energy Regulatory Commission for the Sabine Pass Liquefaction Project in Cameron Parish, Louisiana.

The report covered activities for the Sabine Pass Liquefaction Stage 2 (Trains 3 and 4) and Sabine Pass Liquefaction Stage 3 (Trains 5 and 6) projects that occurred during the month of May 2017.

The report noted Stage 2 Engineering and Procurement are 100% complete. Subcontract and direct hire construction work are 91.0% and 97.1% complete, respectively. Overall project completion for Stage 2 is 98.1% complete against the plan of 100%.

Stage 3 Engineering is now 99.7% complete. Procurement is now 96.2% complete. Subcontract and direct hire work are 47.4% and 26.3% complete, respectively. Stage 3 overall project completion is 67.2% against the plan of 65.7%.

Train 4 is projecting November 2017 for substantial completion. Train 5 is projecting August 2019 for substantial completion.

Sabine LNG Status Report May 2017

Receive the most important LNG headlines in your email inbox each business day. Just sign up for our FREE LNG Headline Daily Newsletter. Sign Up Here.

Share by: