Sabine Pass Liquefaction & Expansion Monthly Progress Report for April, 2017

  • By Admin
  • 24 May, 2017

Train 4 is projecting November 2017 for substantial completion

Train 4 – View From Top of Cryo Rack
Train 4 – View From Top of Cryo Rack
On May 23rd, 2017 Cheniere Energy submitted a monthly construction progress report to the Federal Energy Regulatory Commission for the Sabine Pass Liquefaction Project in Cameron Parish, Louisiana.

The report covered activities for the Sabine Pass Liquefaction Stage 2 (Trains 3 and 4) and Sabine Pass Liquefaction Stage 3 (Trains 5 and 6) projects that occurred during the month of April 2017.

The report noted Stage 2 Engineering and Procurement are 100% complete. Subcontract and direct hire construction work are 88.8% and 97.4% complete, respectively. Overall project completion for Stage 2 is 98% complete.

Stage 3 Engineering is now 99.4% complete. Procurement is now 95.3% complete. Subcontract and direct hire work are 47.2% and 22.3% complete, respectively. Stage 3 overall project completion is 65.4% against the plan of 63.4%. Train 4 is projecting November 2017 for substantial completion. Train 5 is projecting August 2019 for substantial completion.